Fort Dorchester Foundation Outline
Fort Dorchester Site |
The
goal of the Fort Dorchester project was to create a foundation outline that
represented the position of a house that was on the side hundreds of years
ago. A transit was used to establish
elevation points around the foundation.
The primary reference point was taken from the interior of the house
outline. The parks service gave us a map
of the area based on archeological digs, and this information was used to
outline the perimeter of the site.
After set a perimeter of 43 ft. long
across the front, and 34.8 ft. wide along the sides, battering boards were set
at the corners to square the foundation outline. Once the corners were squared, strings were
set forming a width of 20 in. from the outside of the foundation outline to the
inside. This provided an area for the
trenches to be dug around the foundation.
Framing boards were run and leveled forming a 20 in. area for hardcore
(ROC –Crushed Limestone) to be installed in the trenches. The hardcore was installed a tamped down to a
depth of approximately 1/2” below the framing boards. The next step was to pour a 2 –1/2 to 1 mix
of type S mortar over the hardcore. This
provided a stable foundation for the paving bricks that made up the outline of
the foundation.
Crushed Limestone |
Chalk
–lines were used to outline the area for the paving bricks. The dimension for the paving bricks was about
15 3/4 inches. This provided area for
the bricks and a mortar joint, with approximately two inches of foundation on
either side of the pavers. Depending on
the level of the foundation, 3/8” or 1/2” boards were placed along the scribed
guidelines on the foundation. The
purpose being to provide an even mortar bed for the paving bricks. Type S and Type N were used for this process. Once the mortar was poured and leveled with a
screed, the pavers were laid using a 3/8” spacer to establish the joint
width. The joints were backfilled using
a grout bag and tooled after tightening up.
Cleaning the pavers with a sponge and water concluded the foundation
outline.
One of the challenges of the project
was to represent a house that was not there.
The solution that was derived was to build four corners at six courses
high to represent the dimensions of the house.
The corners are two wythe with four bricks on the first course in both
direction. Laying the inside and outside
of the corners simultaneously made it easier to maintain consistent elevation
and level. A story pole was used to
establish the height of the corners.
Half bricks were installed after the majority of the
corner was mortared in, and paver caps were placed on the tops of the bricks to
cover the cores in the bricks and provide a more polished finish. It is important to note that even though this
is a historic site, the materials used are all modern and were not meant to
simulate historic materials.
The final step of the project was
clean the brick work and leave the site in the same, if not better, condition
that we found it in. A low level acid
solution was used to clean the bricks.
The job of the acid was to eat away at the top layer of mortar that had
been left on the bricks and paving foundation.
A hard scrub brush was used to clean the bricks. In order to build up the areas where soil was
removed, soil leftover from archeological digs on the site was used to build up
the along the pavers. This covered any
remnants of the mortar foundation and gave the site a more uniform
appearance. The project has been
considered a success and will hopefully lead to more projects at Historic Fort
Dorchester.
Fort Dorchester Outline Completed |
Jail Courtyard Wall
Courtyard Wall |
Work began on the outdoor theater by installing a foundation pad to the existing outline. The desired area was dug out and boards were
installed to act as levels for the foundation.
In order to use less mortar for the project, stones were placed in the
foundation to trench to act as a filler.
A mortar mix of 1 to 1 was used for the foundation and was pulled off
using a screed. This provided a smooth
and level surface for installing the wall.
After
the foundation was allowed to set, the wall was outlined and scribed in to
provided guidelines for the brick installation.
One of the main focuses of this project was to learn to build
corners. The total number of bricks for
the first course was calculated and a corner was dry stacked at each end of the
foundation. Once the required design was
worked out, the corners were mortared in and line blocks were used to construct
the remaining section of the wall. This
wall was good practice for using different bond patterns. The first three courses were constructed
using a basic running bond. The
remaining three courses consisted of one header course, and two Flemish bond
courses. It was important to make sure
that the overall depth of the wall matched up the length of the bricks we were
using.
Upon
completion of the front side of the wall, attention was turned to construction
a separate, single wythe wall on the back side.
This wall began about half a brick distance from the front side. The back side was good practice at laying
soldier bricks. Seven soldier sections
were left open when the corners of the back wall were constructed. This left space for line blocks to be set
about 1/2” off of the wall face to allow the soldiers to protrude out and give
the wall a sense of depth and design.
The soldiers were buttered and installed in their allotted space. A final stretcher course was laid to cap the
back side of the wall and bring it up to the approximate elevation of the front
side. Slate will be used at a later date
to cap both sections of the wall, thus creating a single wall section that will
be used as seating for the outdoor theater.
Spring 2013 Timber Frame Addition
One of the projects undertaken by the ACBA Trowel Trades program was to construct foundation footings for a 6’ addition to the existing timber –framed shed in the courtyard of the jail. An engineering transit was used to establish the required elevation for the new foundation footings. The transit was set up in the yard, leveled in two directions, and sighted the elevation of the original, outside columns. It was found that there was a 14 –1/2” difference in elevation from the outside of the original post to the sidewalk in the courtyard, and a 3 –1/4” difference in elevation between the center point of the new column location and the side walk. Post 1 of the original structure was the primary elevation reference point. Based on this information, we were able to determine that the space between the ground and the top of the stone cap of the new columns was 13 –1/4.”
String lines were run around the back of the original shed columns to the location of the new columns, which were 6’ from the outside of the existing shed. Battering boards were set up spanning the entire distance of the shed at a distance of 6’ out from the original posts. Additional strings were marked and tied at distances of 5’ 8” from the original post to new column location. This gave us the center point of the new column. A distance of 5’3 –1/4” was measured from the original post to the new to give us the inside point of the new column. A distance of 3 –3/4” was measured from the center point, in two directions, to gives us these points.
When constructing the foundations for the new columns, 24” x 24” holes were dug at a depth of 4” below the required elevation. A wooden peg was driven to mark the desired elevation. Two courses of bricks were laid in a Herringbone pattern to establish the foundation for the new columns. The pattern was dry bonded to make sure that the desired pattern would fit in the given area, and then mortared in once the dimensioned were assured.
The mortar ratio used for the foundation was a 1 to 1 mix because the mortar was old and needed a strong mix to assure a proper bond was formed. After the mortar was allowed to set for period of time, a skim coat of mortar was used to even top of the foundation. This allowed for a flat bonding surface for the brick columns of the new addition. The bricks were dampened with water and a finishing trowel was used to apply the skim coat (same mortar used for skim coat as for the bricks). A two –foot level was placed on the peg marking the required elevation and rotated over the skim coat to make sure the area was level. The next step in preparing the foundation was to use a sponge –float to manicure the skim coat to a uniform texture.
Using the string lines previously established a level and plumb –bob were used to transfer the points to the foundation. The original post dimensions were 8” x 8” and 10” x 10.” The level and plumb –bob were placed just to the outside of corners of the string lines (about 1/16” away from the line) and a pencil was used to mark the points. A small framing square was used to connect the points and scribed into the foundation top. Once the wooden column dimensions were scribed in place, the brick dimension of the columns were marked using the same method. The column of my foundation was 10” x 8”, so the brick outline was 11 –1/2” wide by 13 –1/2” long.
Brick Columns for Timber -Frame Addition
The next phase in the timber –frame addition was the brick columns for the new shed posts. It was determined that 7 course of bricks with 3/8” mortar joints would be required to fill the space between the top of the 4” foundation and the bottom of the 5” stone cap of the columns. The method of dry bond was again employed with wooden spacers simulating the mortar joints.
Once the dimensions were verified, a 2 to 1 mix of Holcim Rainbow Custom Color Buff Mortar Mix was prepared. This was a Type N mortar suitable for masonry above grade.
The brick outline scribed onto the foundation top was used to lay the first course of bricks for the columns. A framing square was used to align the first course of bricks because the it is important to start off in the proper alignment. Upon completion of the first course, a SDS drill was used to bore into the center of the foundation to provide an anchoring point for the new posts. A wooden rod was inserted to prevent mortar filling the hole.
A level was used to make plumb each corner of the column to check the alignment of the columns. Extra mortar was placed around the base of the columns to provide additional strength and stability since soil was used to fill in around the column to get even with the ground level. The process of laying and checking the level and verticality was repeated until all 7 courses were laid.
No comments:
Post a Comment